Hi Oldtimer - if you mean the toothed adjuster nut and the pawl that together make up the ratchet mechanism they are both in good condition. As you say, it's important that there isn't any wear in these or the ratchet self-adjusting mechanism won't work properly and pad wear will not be compensated.
When the parts come back from plating (or to be more precise, when I get round to going to collect them) I will post some pictures as I rebuild the handbrake calipers.
IRS Strip Down and Rebuild
Moderators:davidr, BigCatXJS, dhdove
Re: IRS Strip Down and Rebuild
Hi David, That's exactly what I mean - I'm sure I'm loosing 'me marbles, I just couldn't think of the word "Pawl" - as you say, critical for reliable hand brake auto adjust.
Re: IRS Strip Down and Rebuild
I've been doing a bit more checking on my diff. Got myself some yellow indicator paint and painted it on a few teeth as below
Then I turned the pinion wheel a good few times to see the contact pattern that the pinion teeth left on the crown wheel teeth.
Pattern below on the drive side. This shows the contact patch in the desirable pattern. It is centred on the tooth and there is some clearance between the pattern and the top of the tooth.
The pattern on the coast side was as below This again shows the pattern centred on the tooth but slightly towards the toe and there is some clearance between the pattern and the top of the tooth. That's the ideal pattern.
So happy days, my diff has passed the tests so I can give it another coat of paint and replace the backplate then its ready to be built up again.
Pattern below on the drive side. This shows the contact patch in the desirable pattern. It is centred on the tooth and there is some clearance between the pattern and the top of the tooth.
The pattern on the coast side was as below This again shows the pattern centred on the tooth but slightly towards the toe and there is some clearance between the pattern and the top of the tooth. That's the ideal pattern.
So happy days, my diff has passed the tests so I can give it another coat of paint and replace the backplate then its ready to be built up again.
XJS FORUM COORDINATOR
1996 XJS Celebration Convertible 2001 XKR Convertible
Previously enjoyed!
1989 XJ-S V12 Coupe. 2006 XJ TDVi Sovereign. 1995 XJ6 3.2. 2013 XF 2.2d. 2009 X Type 2.0d Sovereign estate
1996 XJS Celebration Convertible 2001 XKR Convertible
Previously enjoyed!
1989 XJ-S V12 Coupe. 2006 XJ TDVi Sovereign. 1995 XJ6 3.2. 2013 XF 2.2d. 2009 X Type 2.0d Sovereign estate
Re: IRS Strip Down and Rebuild
I also stripped down my hubs to see the state of the roller bearings. First I drove the hub out of the carrier. Nothing sophisticated about it - I just hold the hub carrier in the vice and using a suitably sized socket and a 1/2" extension percussion is applied to the hub. Sorry - forgot to take a picture of that bit!
As mine is an ABS car the next thing was to pull off the ABS ring. This is pressed on and has to be CAREFULLY pulled off. It's important not to try to hit it off as it's quite brittle. I used a three leg puller as below. Mine both pulled off smoothly but I was very careful not to be too brutal with them. Having looked at the bearings and the rust colour in the grease together with the fact that the bearings were noisy and notchy when I turned them convinced me that I should change them. So they have to come off.
My preferred method is to first put a chisel through as below. The state of the rollers and the rust in them can be seen here Having cut the roller carrier through with the chisel it can be removed to expose the inner race.
Then is use a grinder to remove as much as I dare. The idea isn't to grind it away completely but to thin it enough that I can crack it with a chisel. Obviously this has to be done carefully so as not to damage the hub. You'll see here that I nicked it slightly a couple of times but nothing serious. Cracking it enables it to be opened up slightly and it can be levered off. The inner race can then be opened up a bit and levered off This leaves the hub to be cleaned up.
New bearings on order!
As mine is an ABS car the next thing was to pull off the ABS ring. This is pressed on and has to be CAREFULLY pulled off. It's important not to try to hit it off as it's quite brittle. I used a three leg puller as below. Mine both pulled off smoothly but I was very careful not to be too brutal with them. Having looked at the bearings and the rust colour in the grease together with the fact that the bearings were noisy and notchy when I turned them convinced me that I should change them. So they have to come off.
My preferred method is to first put a chisel through as below. The state of the rollers and the rust in them can be seen here Having cut the roller carrier through with the chisel it can be removed to expose the inner race.
Then is use a grinder to remove as much as I dare. The idea isn't to grind it away completely but to thin it enough that I can crack it with a chisel. Obviously this has to be done carefully so as not to damage the hub. You'll see here that I nicked it slightly a couple of times but nothing serious. Cracking it enables it to be opened up slightly and it can be levered off. The inner race can then be opened up a bit and levered off This leaves the hub to be cleaned up.
New bearings on order!
XJS FORUM COORDINATOR
1996 XJS Celebration Convertible 2001 XKR Convertible
Previously enjoyed!
1989 XJ-S V12 Coupe. 2006 XJ TDVi Sovereign. 1995 XJ6 3.2. 2013 XF 2.2d. 2009 X Type 2.0d Sovereign estate
1996 XJS Celebration Convertible 2001 XKR Convertible
Previously enjoyed!
1989 XJ-S V12 Coupe. 2006 XJ TDVi Sovereign. 1995 XJ6 3.2. 2013 XF 2.2d. 2009 X Type 2.0d Sovereign estate
Re: IRS Strip Down and Rebuild
Hi David,
You are doing a fine job , the crown wheel mesh as demonstrated by the dye looks spot on. What others may not fully understand is that this is a hypoid gear arrangement in that as one tooth of the pinion enters mesh with the crown wheel while the next tooth is fully engaged and the third tooth is just leaving the crown wheel so the load is spread. Prior to the hypoid or angular change of engagement only one crown wheel tooth and one pinion tooth engaged at any one time.
Will " her in doors " let you put the hubs in the freezer, then heat the bearing inner race to assemble them a little easier ?
wish I was there to help - well, maybe make the tea !
Love the thread you are running with some great photo's , keep up the good work
Oldtimer
You are doing a fine job , the crown wheel mesh as demonstrated by the dye looks spot on. What others may not fully understand is that this is a hypoid gear arrangement in that as one tooth of the pinion enters mesh with the crown wheel while the next tooth is fully engaged and the third tooth is just leaving the crown wheel so the load is spread. Prior to the hypoid or angular change of engagement only one crown wheel tooth and one pinion tooth engaged at any one time.
Will " her in doors " let you put the hubs in the freezer, then heat the bearing inner race to assemble them a little easier ?
wish I was there to help - well, maybe make the tea !
Love the thread you are running with some great photo's , keep up the good work
Oldtimer
Re: IRS Strip Down and Rebuild
Hi Oldtimer - thanks for your post about hypoid gears - I learnt something there.
As for freezing the hub, I'm afraid that she who must be obeyed has a very low tolerance for finding car parts in the freezer!
But I do have an hydraulic press which makes this job much easier so long as all the parts are clean with no burrs or sharp edges. A little light grease works wonders too.
I'm working away all week and helping my daughter move house all weekend so the next instalment will have to wait. I've ordered the bearings but I'm also considering having the alloy hub carriers and the diff rear plate vapour blasted. I've cleaned them up pretty well but vapour blasting would give them a really nice finish. Or am I getting too tarty about this job now?!!
Best wishes
David
As for freezing the hub, I'm afraid that she who must be obeyed has a very low tolerance for finding car parts in the freezer!
But I do have an hydraulic press which makes this job much easier so long as all the parts are clean with no burrs or sharp edges. A little light grease works wonders too.
I'm working away all week and helping my daughter move house all weekend so the next instalment will have to wait. I've ordered the bearings but I'm also considering having the alloy hub carriers and the diff rear plate vapour blasted. I've cleaned them up pretty well but vapour blasting would give them a really nice finish. Or am I getting too tarty about this job now?!!
Best wishes
David
XJS FORUM COORDINATOR
1996 XJS Celebration Convertible 2001 XKR Convertible
Previously enjoyed!
1989 XJ-S V12 Coupe. 2006 XJ TDVi Sovereign. 1995 XJ6 3.2. 2013 XF 2.2d. 2009 X Type 2.0d Sovereign estate
1996 XJS Celebration Convertible 2001 XKR Convertible
Previously enjoyed!
1989 XJ-S V12 Coupe. 2006 XJ TDVi Sovereign. 1995 XJ6 3.2. 2013 XF 2.2d. 2009 X Type 2.0d Sovereign estate
Re: IRS Strip Down and Rebuild
Hello David,
the old way was to use an old pan or the like with oil and heat that up to a couple of hundred degrees and immerse the bearing, then fit. Much less chance of damaging it than using a blowtorch or the like.
Alec
the old way was to use an old pan or the like with oil and heat that up to a couple of hundred degrees and immerse the bearing, then fit. Much less chance of damaging it than using a blowtorch or the like.
Alec
Mk 2 3.8 (long term restoration), MK1 Triumph 2.5 P.I. , 564 Hymer Motorhome
Re: IRS Strip Down and Rebuild
David,
Great pics and descriptions - really enjoying this thread!
Paul
Great pics and descriptions - really enjoying this thread!
Paul
1995 XJS 4.0 Convertible
1980 XJ-S Pre-HE
Jaguar 4.2 Supercharged engine (but not with a Jaguar body..)
1980 XJ-S Pre-HE
Jaguar 4.2 Supercharged engine (but not with a Jaguar body..)
Re: IRS Strip Down and Rebuild
Yes David, you're getting too tarty, but I like it. I've used aluminium paint on aluminium parts which looks ok and seems to last quite well.
Re: IRS Strip Down and Rebuild
It sounds brutal but I use dilute hydro-chloric acid to really get ali parts spotlessly clean. An old paint brush gets the grot off very quickly followed by a running water wash/scrub with Scotchbright does the rest. Parts I`ve cleaned in this way don`t seem any the worse for the treatment. I`ve used the method for years cleaning up S-type, XF and X350 suspension wishbones prior to refurbishment.
Here are a pair of acid cleaned and refitted X350 lower rear wishbones I built for young PTJS1. Indistinguishable from new. Five litres of 36% acid comes from ebay for around £11.
Elfin Safety. Add acid to water when diluting. NOT the other way around! Wear PPE gear to avoid acid attack!!!!!
Mike K
Here are a pair of acid cleaned and refitted X350 lower rear wishbones I built for young PTJS1. Indistinguishable from new. Five litres of 36% acid comes from ebay for around £11.
Elfin Safety. Add acid to water when diluting. NOT the other way around! Wear PPE gear to avoid acid attack!!!!!
Mike K
X350 Co-ordinator
2004 XJR
2004 XJR
Re: IRS Strip Down and Rebuild
Thanks Mike - I have ordered some of this from Frost Restoration. Working on the same principle I guess. I'll report back when I've tried it!
http://www.frost.co.uk/media/catalog/pr ... v135_1.jpg
http://www.frost.co.uk/media/catalog/pr ... v135_1.jpg
Re: IRS Strip Down and Rebuild
Mike , Have never thought of that. Must try and remember that !!! Is it battery acid ?
Re: IRS Strip Down and Rebuild
Battery acid is sulfuric acid, Phil. Just as evil and potentially dangerous. Take extreme care if you decide to experiment. Add the acid to water, not the other way around. It tends to jump out at you!
High acid concentrations can generate considerable heat. Expect it to get a little warm if not hot when parts are being cleaned. Stout, acid proof gloves, eye protection etc, etc whenever you have anything to do with this type of chemical. I have a bucket of water close by when using such a brew. Acid is quite able to break down human flesh. Remember John James Haig, the last man to be hung in Britain? Dissolved his victims in an oil drum full of acid leaving only teeth to dispose of. Not a man to be left alone with...rather like Hanibal Lector who enjoyed having a friend for dinner!
Mike
High acid concentrations can generate considerable heat. Expect it to get a little warm if not hot when parts are being cleaned. Stout, acid proof gloves, eye protection etc, etc whenever you have anything to do with this type of chemical. I have a bucket of water close by when using such a brew. Acid is quite able to break down human flesh. Remember John James Haig, the last man to be hung in Britain? Dissolved his victims in an oil drum full of acid leaving only teeth to dispose of. Not a man to be left alone with...rather like Hanibal Lector who enjoyed having a friend for dinner!
Mike
X350 Co-ordinator
2004 XJR
2004 XJR
Re: IRS Strip Down and Rebuild
Silly Me, Of Course it is.
Re: IRS Strip Down and Rebuild
I've used the Frost Ali-Clean on my hub carriers and diff back plate.
they came out like this
The hub carriers have come out quite well but most of this is the result of elbow grease in giving them a really good clean.
The diff back plate was, if anything, dulled a little by it.
What I did notice was that the machined surfaces went streaky - this is only good for rough cast alloy.
they came out like this
The hub carriers have come out quite well but most of this is the result of elbow grease in giving them a really good clean.
The diff back plate was, if anything, dulled a little by it.
What I did notice was that the machined surfaces went streaky - this is only good for rough cast alloy.